The codified FAR still puts tradeoff and lowest price technically acceptable at 15.101-1 and 15.101-2. More than 30 agencies, DoD among them, have adopted the rewritten Part 15 through class deviations, and that text moves source selection to FAR 15.103 and names three approaches instead of two. This post compares tradeoff, lowest price technically acceptable (LPTA) and the new highest technically rated option, lays out the separate civilian and DoD limits on LPTA, and lists what the file should show for each.
What is the difference between best value tradeoff and LPTA?
A tradeoff lets the government award to other than the lowest priced or other than the highest technically rated offeror, and a higher priced proposal can win when its benefits merit the extra cost. LPTA awards to the lowest priced proposal that meets every acceptability standard, and no tradeoffs are allowed. Both are ways to reach best value; they differ in whether better than acceptable is worth paying for.
In a tradeoff, the evaluation assesses each offeror's ability to do the work and records relative strengths, deficiencies, significant weaknesses and risks (15.202(b)(2) in the deviation text). Proposals can be ranked. In LPTA, proposals are evaluated for technical acceptability only, and the RFP must say award goes to the lowest evaluated price among acceptable proposals (15.103-2(b)).
The codified FAR frames the choice the same way. FAR 15.101 calls it a "best value continuum": price "may play a dominant role" when the requirement is clearly definable and performance risk is minimal, and technical or past performance considerations may dominate as the requirement gets less definitive or riskier.
What changed in the rewritten FAR Part 15?
The model deviation text for Part 15 was issued September 30, 2025, according to acquisition.gov's deviation guide. It moves source selection approaches to 15.103 and adds two named options: highest technically rated with a fair and reasonable price (15.103-3) and phased acquisition (15.103-4), which splits a complex or high-risk buy into separate awards at distinct phases. The section also says agencies may use "any one or a combination" of approaches, "including but not limited to" the ones listed.
One familiar sentence moved rather than disappeared. Codified FAR 15.101-1(b)(2) requires a tradeoff solicitation to state whether all non-cost factors combined are "significantly more important than, approximately equal to, or significantly less important than cost or price." The deviation puts that requirement in 15.104(d), "Factor importance," citing 10 U.S.C. 3206(c)(1)(C) and 41 U.S.C. 3306(c)(1)(C), and applies it to competitive RFPs generally rather than only to tradeoffs. The one exception is the DoD, NASA and Coast Guard case in 15.104(b)(1)(ii), where a multiple-award RFP for the same or similar services, above the simplified acquisition threshold and intending awards to all qualifying offerors, may leave price out as an award factor and consider it at the order level instead.
The deviation applies at an agency only once that agency issues its own class deviation. The deviation guide lists Part 15 deviations from more than 30 agencies, including DoD, GSA, HHS, DHS, VA, HUD and Treasury; DoD readers should also check DoD's current DFARS and deviation text. Part 15 is among the parts in a proposed rule published September 18, 2026 (FAR Case 2026-003), whose comment period closed October 19. As of November 15, 2026, the Federal Register lists no final rule for it. Our post on where the FAR overhaul stands explains how the deviations and proposed rules fit together.
When can an agency use LPTA?
Outside DoD, only when six conditions are met and the contracting officer documents why. They come from section 880 of the John S. McCain National Defense Authorization Act for Fiscal Year 2019, and they appear in both the codified FAR 15.101-2(c) and the deviation's 15.103-2(c). DoD follows its own list in DFARS 215.101-2-70, drawn from section 813 of the FY2017 NDAA as amended.
| Condition | Civilian (FAR, section 880) | DoD (DFARS 215.101-2-70) |
|---|---|---|
| Minimum requirements described clearly and comprehensively in performance terms | Yes | Yes |
| No, or minimal, value from exceeding the minimum | Yes | Yes |
| No, or minimal, subjective judgment needed to compare proposals | Yes | Yes |
| High confidence that reviewing all proposals would not reveal added value | Yes | Yes |
| Lowest price reflects total cost | Yes, including operation and support | Yes, as a file determination on full life-cycle costs |
| No, or minimal, added innovation or future technological advantage from another approach | Not listed | Yes |
| Goods predominantly expendable, nontechnical or short-lived | Not listed | Yes |
| Contracting officer documents the circumstances justifying LPTA | Yes | Yes |
Both texts then tell contracting officers to avoid LPTA "to the maximum extent practicable" for procurements predominantly for information technology services, cybersecurity services, systems engineering and technical assistance, advanced electronic testing and other knowledge-based professional services. Both also cover personal protective equipment and knowledge-based training or logistics services in contingency operations or other operations outside the United States. Only the civilian list names audit or audit readiness services, health care services and records, and telecommunications devices and services.
DFARS goes further with outright prohibitions: no LPTA for an auditing contract (10 U.S.C. 240f); for personal protective equipment or an aviation critical safety item when the requiring activity advises that the level of quality or failure could result in combat casualties; or for engineering and manufacturing development of a major defense acquisition program for which budgetary authority is requested beginning in fiscal year 2019.
How does the highest technically rated approach work?
The agency decides in advance that price tradeoffs would not be advantageous and that the requirement warrants paying any fair and reasonable price for the highest quality performance. Proposals are evaluated on the non-price factors, and the source selection authority identifies the highest rated one. Its price is then tested for fairness and reasonableness under subpart 15.4.
If the price passes, that proposal wins. If not, the authority moves to the next highest rated proposal and repeats the price test until award goes to the highest technically rated responsible offeror with a fair and reasonable price. The RFP must tell offerors up front that no tradeoffs will be made and that the highest technically rated proposal will be selected if its price is fair and reasonable (15.103-3(b)).
For offerors, this changes the pricing question. There is no credit for being cheaper than a stronger competitor, but a price the government finds unreasonable sends the evaluation down the list.
Which approach fits an IT or cybersecurity requirement?
For most knowledge-based IT work, the regulations point away from LPTA, so in practice the choice is often between a tradeoff and the highest technically rated approach. A tradeoff fits when the agency wants to weigh how much better a proposal is against how much more it costs. Highest technically rated fits when the agency has already decided quality should drive the award and the remaining question is whether the price is fair.
LPTA can still fit a narrow, well-specified piece of a larger effort, such as a well-defined product buy, where every civilian condition holds and nothing above the minimum adds value. The market research file is where that case usually gets made or lost: it shows whether the requirement is stable, whether the market offers meaningful differences, and whether paying for more would buy anything.
What should the source selection file show?
Whichever approach is chosen, the file should let a reviewer trace the award back to the RFP. The deviation's 15.205 requires the source selection decision to reflect the source selection authority's independent judgment, compare proposals against all the criteria in the RFP, and document the rationale for business judgments and tradeoffs, "including benefits associated with additional costs." It adds that the documentation "does not need to quantify the tradeoffs."
For a tradeoff, that means naming the specific strengths that justify a higher price, not repeating adjectival ratings. For LPTA, good practice is a written finding on each of the six (or, at DoD, eight) conditions, plus the record that each acceptable proposal met every standard. For highest technically rated, it means the ranking, the price reasonableness analysis for the winner and, where it happened, for each proposal that was passed over on price.
From our delivery teams: Write the LPTA justification as one short paragraph per condition, each tied to evidence already in the file (the performance standards, the market research, the life-cycle cost analysis). A reviewer checking conditions one by one finds the answer where they expect it.
For offices rethinking how that record gets built, AIR-Quire drafts the FAR-required acquisition documents, checks every step against the agency's rules and compiles a complete, reviewable record, with a person in charge of every decision.
The Bottom Line
Pick the approach from the requirement and the market research, not from habit, and make the file show why. For IT and cybersecurity services, the statute tells civilian agencies to avoid LPTA to the maximum extent practicable, and the highest technically rated approach is now a named option when quality matters more than price tradeoffs. Which approach fits a given buy is the contracting officer's call under the agency's own deviation.
FAQ
Can an agency use LPTA for IT services?
For civilian agencies, the FAR text implementing section 880 of the FY2019 NDAA says contracting officers must avoid LPTA "to the maximum extent practicable" when a buy is predominantly for information technology, cybersecurity or other knowledge-based professional services. It is not an outright ban, so the contracting officer decides and documents the file. DoD's DFARS 215.101-2-70 contains a similar avoidance list.
What is the highest technically rated with a fair and reasonable price approach?
It is a source selection approach named at 15.103-3 in the rewritten FAR Part 15. Proposals are ranked on the non-price factors, and the top proposal wins if its price is fair and reasonable; if not, the evaluation moves to the next highest rated. The RFP must tell offerors in advance that no tradeoffs will be made and that the highest technically rated proposal will be selected if its price is fair and reasonable.
Does a tradeoff decision have to put a dollar value on the difference between proposals?
The deviation text at 15.205 says the source selection decision must document the rationale for business judgments and tradeoffs, including the benefits associated with additional costs, and that the documentation "does not need to quantify the tradeoffs." The reasoning still has to be on paper.
Is past performance evaluated in an LPTA source selection?
It can be. Under the deviation's 15.202(c)(2), if past performance is evaluated in an LPTA buy, the contracting officer only determines whether it is acceptable and does not compare offerors. If a small business in contention is found unacceptable on past performance, 15.202(c)(4) requires referral to the SBA for a Certificate of Competency determination.
Which FAR numbering should a solicitation use?
It depends on whether the agency has issued its own class deviation for Part 15. The codified FAR on acquisition.gov still shows 15.101-1 and 15.101-2, while the deviation text uses 15.103. Read the solicitation against the version the agency adopted and ask the contracting officer when it is unclear.
Sources
- Acquisition.gov, FAR Overhaul Part 15, Contracting by Negotiation (model deviation text)
- Acquisition.gov, FAR 15.101-1 Tradeoff process
- Acquisition.gov, FAR 15.101-2 Lowest price technically acceptable source selection process
- Acquisition.gov, DFARS 215.101-2-70 Limitations and prohibitions
- Acquisition.gov, FAR Overhaul FAR Part Deviation Guidance
- Federal Register, Revolutionary FAR Overhaul Parts 8, 12, 13, 15, 38, 44, and 51 (proposed rule, September 18, 2026)
How we researched this. Every number, date and requirement here is checked against the sources listed above, primary documents first, and the post is fact-checked again before publication. When a rule, date or status changes, we update the post and log the change below. Read our editorial standards or send a correction.